Rooted in a Strong Foundation

Rising to Support Our Future Generations

St. Laurence Church is building a new Parish Hall, called The Great Hall, and refurbishing the old Parish Hall into our new Children’s Ministry Building.

Spaces are being created where we can all gather, where we can serve, teach, our youth can grow and where the mission of the Church can flourish. God has brought us tremendous growth and through Him, this expansion is possible.

Follow along here where you’ll find the last 4 weeks of progress updates with pictures. To see the log of all updates for the entire project, click the button below.

Expansion Log

  • Work began on construction of the vehicle bridge over the creek. 12 massive concrete culvert boxes have been installed. 

  • In The Great Hall, we are continuing work on masonry brick installation, exterior siding, and interior HVAC ducting. 

  • In the Children’s Ministry Building, finish out continues, including HVAC, electrical, fire sprinkler control, painting, ceiling, and interior doors. Also, installation of exterior storefront windows and door frames have begun. The exterior stone installation is nearly complete. 

Dec. 21


  • In The Great Hall, the shingle installation on the roof continues, the interior HVAC ducting continues and the finish up on the fire control sprinkler system is near. 

  • In the Children’s Ministry Building, the exterior stone work continues, the ceiling tile grid is nearly completed and the interior light installation has begun.  

  • Excavation for the Driving Bridge began

Dec. 14


  • In The Great Hall, brick work on the south wall is completed and exterior sheathing continues. Roofing insulation and decking continues plus shingle installation has begun, installation of the fire sprinkler system continues. 

  • In the Children’s Ministry Building, the first coat of paint went on the transept trusses and inside walls, stone masonry work has begun, and installation of the interior ceiling grid has begun.

Dec. 7


  • Framing, exterior sheathing, brick work and sprinkler system work all continue on The Great Hall. 

  • In the Children’s Ministry Building, bathroom tile work has begun and drywall tape and bedding continues.

Nov. 30